How Do I Hide Lines In MS Project?

How do I hide inactive tasks in MS Project?

Inactive tasks appear dimmed with a strikethrough.

You can easily hide inactive tasks by filtering them out.

On the View tab, in the Data group, click the arrow next to Filter, and then click Active..

How do you expand rows in MS Project?

Click the View tab on the Ribbon, click the Show Outline button in the Data group, and then click Show Subtasks. Click the View tab on the Ribbon, click the Show Outline button in the Data group, and click the level of the outline you want to reveal for the entire outline.

How do I hide summary task in MS Project?

Show the project summary task in Project desktopOn the Tools menu, click Options, and then click the View tab.Under Outline options, select or clear the Show summary tasks check box to show or hide the project summary task.

How do I show hidden tasks in MS Project?

To display hidden subtasks in a task view such as the Gantt Chart in Project 2007 and earlier versions, follow these steps:On the View menu, click Gantt Chart.Click the heading of the Task Name column to select all tasks.On the Project menu, point to Outline, point to Show, and then click All Subtasks.

How do I print a Gantt chart without the timeline?

On the View menu, click More Views. Select Gantt Chart, and click Apply. On the View menu, click Table, and then click No Table Info. On the File menu, click Print or Print Preview.

Link tasks by using the Gantt Chart viewOn the View menu, choose Gantt Chart.In the Task Name field, select two or more tasks you want to link, in the order you want to link them. To select nonadjacent tasks, hold down CTRL and select the tasks you want to link. … Choose Link Tasks .

What is summary task in MS Project?

In Microsoft Project, a summary task that is also called a parent task is a collection of subtasks that shows their combined information. The indented tasks or following tasks of the summary task are called subtasks.

How do I expand all tasks in MS Project?

Yes, you should be able to expand all tasks at View > Data group > Outline > All Subtasks. However, this will only allow you to expand all, as far as I know, there is no way to collapse all subtasks unless you do a non-contiguous selection of all level 2 tasks and then do a Hide Subtasks.

How do I hide a Gantt chart in MS Project?

Project Server – you cannot hide the gantt bars in project center.Project Online – you can hide the gantt bars in the project center – just choose the option from the ribbon in PWA.MS Project – change the view to the task sheet and add in the columns you want.